The FDE Decomposition Round: Vague Ask to a Plan

This plan sounded fine. A 53-line checker found eight holes in it.

1. A decomposition interview round gives you a vague, real world problem. What is it scored on, according to prep-site guides?
2. In a Python plan checker demo, the checker looked at a first plan for the made-up ask make our support team faster. How many problems did it find in the first plan, and how many in the second plan?
3. How does a Python plan checker work out how many days a plan takes when tasks do not all depend on each other?
4. Why does a plan checker for a decomposition interview ask whether any metric mentions the word baseline?
5. A plan checker reports zero problems for a plan. What does that tell you?

Practice only: nothing is saved and no score counts towards anything. Each answer comes with the reason.

  1. Read the eight problems

    Copy the code folder first. Read FIRST_PLAN in plans.py and list the problems you can see yourself: owners, metrics, data sources and what each task waits for. Then run python run.py and compare your list with the 8 problems it prints. Which ones did you miss?

    A hint

    Check the SOURCES table for which data exists and which access is pending.

  2. Tighten the budget

    In plans.py change BUDGET_DAYS from 30 to 20, then run python run.py. Predict what the second plan reports. You should see 1 problem, that it takes 25 days when the budget is 20. Change BUDGET_DAYS back to 30 afterwards.

    A hint

    The second plan is one chain, so its days add up to 25.

  3. Remove the baseline

    In the second plan change the metric of T1 from baseline recorded to time recorded, then run python run.py. Predict the result. You should see 1 problem, that nothing measures how things are today. Why is that check about the word baseline and not about the number of metrics? Change the metric back to baseline recorded afterwards.

    A hint

    The check looks for the word baseline in any metric of the plan.

  4. Use data you may not touch yet

    In the second plan change the source of T3 from chat logs to crm, then run python run.py. You should see 1 problem about access to crm being pending. Change it back, then change the days of T2 from 4 to 10 and predict the new problem. You should see that the plan takes 31 days against a budget of 30. Change the days of T2 back to 4 afterwards.

    A hint

    The crm entry in SOURCES has pending access, and the days of one chain add up.

  5. Run two tasks in parallel

    In the second plan make T2 independent by changing its needs from T1 to an empty list. Predict the finish time using the critical path, then run python run.py. You should see 22 days. Explain why it is less than 25.

    A hint

    T1 and T2 no longer wait for each other, so the longest chain is T2, T3, T4.

These tasks are for you to try on your own machine. Nothing is checked or saved.

What this does not show

Made-up customer and plans; the first plan was written with its holes on purpose. The checks cannot tell whether a metric or an owner is a good one. A real round is a conversation.